requirement_id,owner_phase,initial_evidence,status
R-001,10,package reconstruction record,planned
R-002,8,session acceptance test,planned
R-003,9,performance benchmark record,planned
R-004,6,controller compatibility matrix,planned
R-005,7,provider contract and acceptance tests,planned
R-006,2,CLI integration tests,planned
R-007,8,gaming-tool integration tests,planned
R-008,8,session lifecycle acceptance test,planned
R-009,1,core contract tests,planned
R-010,5,TTY recovery acceptance test,planned
R-011,0,development workflow record,active
R-012,1,shared-backend architecture tests,planned
R-013,8,profile policy acceptance tests,planned
R-014,12,Pegasus adapter tests,post-v1
R-015,8,Lean and Ready policy tests,planned
R-016,7,adapter capability contract tests,planned
R-017,8,window-switching acceptance tests,planned
R-018,4,lifecycle confidence tests,planned
R-019,15,vendor launcher tests,post-v1
R-020,6,Bluetooth CLI and TUI tests,planned
R-021,11,installer destructive VM tests,planned
R-022,10,optional recovery profile tests,optional
R-023,14,OpenGamepadUI evaluation,post-v1
R-024,1,adversarial contract tests,planned
R-025,0,source inventory and release review,active
R-026,0,supported-platform record,active
R-027,0,path and identity architecture review,active
R-028,8,release GPU matrix,planned
R-029,1,TOML and JSON contract tests,planned